Beaver Mines Project Recap

Below is a recap of information relating to the Beaver Mines Water/Waste Water Project. For any further information please contact the MD at 403 627 3130 or email info@mdpinchercreek.ab.ca

October 4, 2023
 
The MD of Pincher Creek will begin allowing permanent connection to the water and wastewater system within the Hamlet of Beaver Mines starting October 6th, 2023.
 
Connection within the Hamlet of Beaver Mines for all developed properties adjacent to a Distribution System Water Main and Wastewater Main will be mandatory by January 1st, 2028.
 
The attached letter contains further details and should be read in full.

Letter

September 25, 2023

STAGE 3 – EXTREME WATER RESTRICTION & OLDMAN RESERVOIR WATER SUPPLY
The MD remains in a mandatory Stage 3 - Extreme water restriction. See our website for further details.
 
The MD is continuing to maintain our water supply with Alberta Government approval by trucking water and is working diligently on short and long term solutions. See our website for additional details (Municipal District of Pincher Creek No. 9 (mdpinchercreek.ab.ca). The Beaver Mines standpipe remains shutdown; Pincher Creek remains open as it is on a different water supply.

GETTING CONNECTED
Anticipated Flow Allowance Date
As of September 22nd, the MD is anticipating acceptance of flow between September 27th and October 6th, 2023.



The delay from the previous updates is the result of longer than anticipated water haul times for commissioning, and the need to fix construction related deficiencies found during initial fill/commissioning of the wastewater treatment system.
 
Please note that owners must not connect to the curbstops and stubbed sewer connection until the treatment system is able to take flows. The MD will issue the exact date when it is ready to allow final connection to the system. Owners MUST NOT connect before this date. Owners must also submit an application and follow the approval process outlined below.
 
Homeowner Connection Guide
This guide is intended to be the main resource to assist homeowners in navigating the connection process. It can be found on the MD website (https://mdpinchercreek.ab.ca/content.php?p=730).
 
Utility Services Guidelines
A copy of the Utility Services Guidelines can be found on the MD website (https://mdpinchercreek.ab.ca/content.php?p=730). These guidelines provide the minimal acceptable procedures and standards to be followed for design and install of private water and drainage (sewer) lines. They are intended to inform both contractors and property owners.
 
Pre-Qualified Contractors
The MD has updated has updated its website with additional pre-qualified contractors  since the last update (https://mdpinchercreek.ab.ca/content.php?p=731). Use of pre-qualified contractors is not mandatory, but meeting USG requirements is mandatory.
 
Service Connection Application
A private service connection application must be completed with a new site plan and submitted digitally to admininfra@mdpinchercreek.ab.ca or dropped off in person at the MD office. Blank copies of the new site plans with curbstop information have been mailed to the majority of residents, along with copies of the original service cards received by the MD in 2019 (where ownership has not changed) for ease of reference. There are a few residents whom have not been mailed site plans yet. We have just received these digitally (email the MD to request) and will be mailing them shortly.
 
If additional guidance is required in this process, please refer to the Homeowner Connection Guide as a first step. Those having trouble accessing links or finding pages on the website may email the MD and request copies of the documents be emailed to them. Alternatively, hard copies of any documents (including site plans) may be picked up from the MD office.
 
PROJECTS UPDATE
The following progress has been made on the Beaver Mines water and wastewater projects:

September 9, 2023

The MD’s contractors for the Beaver Mines Wastewater Treatment site plan to begin the initial fill and test of the treatment cells starting September 11th. This process is anticipated to take 10-14 days.
 
During this time there will be increased traffic from water and water effluent hauling trucks in the Hamlet of Beaver Mines. Water and water effluent trucks will be dumping directly into the sewage collection system.
 
Please exercise extra caution when driving and walking around the Hamlet during this time.
 
July 18, 2023

Updated Frequently Asked Questions

July 18, 2023

Project Update

July 14, 2023

Construction Update

July 6, 2023

Construction Update

June 29, 2023

Construction Update

June 23, 2023

Construction Update

June 22, 2023

Beaver Mines Frequently Asked Questions

June 19, 2023

Notice of Construction

June 9, 2023

Notice of Construction

June 1, 2023

Thank you for your patience as BYZ continues to progress on the completion of this project. Please refer to the map below for projected sequencing and upcoming activities. For the safety of the public, please be cautious of moving equipment and refrain from walking within the construction work zone.

Construction Update

May 25, 2023

Thank you for your patience as BYZ continues to progress on the completion of this project. Please refer to the map attached for projected sequencing and upcoming activities. For the safety of the public, please be cautious of moving equipment and refrain from walking within the construction work zone.

Construction Update

May 19, 2023

The below notice contains important information for residents and businesses along the East and Southeast side of the highway in Beaver Mines relating to clearing and grubbing.
 
As part of BYZ’s contract, fencing will be installed along the East and Southeast border of the Hamlet on property line for properties highlighted in yellow in the attached sketch. This will require additional clearing/grubbing adjacent to various properties.
 
Please note that along the Southeast side of the Hamlet the fence will be installed along Southeast border of the MD laneways. If there are any concerns regarding off-property encroachments and clearing please respond and let us know prior to May 29th.

Notice of Clearning
 
May 12, 2023

Thank you for your patience as BYZ continues to progress on the completion of this project. Please refer to the map below for projected sequencing and upcoming activities. For the safety of the public, please be cautious of moving equipment and refrain from walking within the construction work zone.

Note: Once Sanitary main services are completed, BYZ will be working to restore the ditches and will notify when the paving portion will be started.

CONSTRUCTION UPDATE

April 21, 2023

Please refer to the attached map for projected sequencing and upcoming activities for the continuation of Construction on the Beaver Mines Water and Wastewater Collection and Distribution System.
 
BYZ intends to start full mobilization again next week, and (weather pending) start underground work again May 1st, 2023.
 
The MD of Pincher Creek continues to plan for and remains optimistic that the bulk of construction work for Beaver Mines related projects will finish this year. A “turning on the taps” date is still anticipated to occur in Fall 2023. We plan to release more details regarding the processes and permitting requirements (Utility Services Guidelines) for connection to the system, along with the related pre-qualified contractor process, within the coming month.
  
Council and staff thank the community for its patience.
 
If you have any specific questions or concerns, please contact the office at 403 627-3130.

Notice of Construction - April 21, 2023


March 14, 2023

Updated Frequently Asked Questions
Beaver Mines Resident Letter
Utility Bylaw 1344-22

February 23, 2023

The MD Council heard comments and concerns and made changes to the proposed bylaw prior to 2nd reading. 3nd reading of the bylaw is scheduled for Council deliberation at the regular meeting of council February 28th, 6PM at the MD Council Chambers (1037 Herron Avenue). 3rd reading is required before a bylaw can go into effect.
 
The following critical changes from the path laid out in the November 2nd, 2022 letter to property owners are as follows:
 
1)            Requirements regarding alternate water source decommissioning (i.e. wells) removed from bylaw. Connection to the water and wastewater system will remain mandatory and alternate water systems cannot be connected/have the ability to “cross-flow” with the municipal system
2)            The proposed utility bylaw waives the cost of supplying the meter for owners whom connect to the system within 9 months of the MD’s allowed connection date (previously 30 days)
 
Bylaw being presented for 3rd reading

February 10, 2023

A public hearing was held January 10th, 2023 regarding Utility Bylaw 1344-22 which will affect water and wastewater servicing within the Hamlet of Beaver Mines. We thank all the property owners whom took the time to attend the hearing and/or send in comments regarding the bylaw.
 
The MD Council heard comments and concerns and has made changes to the proposed bylaw. 2nd reading of the bylaw with proposed changes is scheduled for Council deliberation at the regular meeting of council February 14th, 6PM at the MD Council Chambers (1037 Herron Avenue). 2nd and 3rd reading are required before a bylaw can go into effect.

The following critical changes from the path laid out in the November 2nd, 2022 letter to property owners are as follows:

  1. Requirements regarding alternate water source decommissioning (i.e. wells) removed from bylaw. Connection to the water and wastewater system will remain mandatory and alternate water systems cannot be connected/have the ability to “cross-flow” with the municipal system
  2. The proposed utility bylaw waives the cost of supplying the meter for owners whom connect to the system within 9 months of the MD’s allowed connection date (previously 30 days)

Utility Bylaw - 2nd Reading

December 14, 2022

2022-12-01 Beaver Mines Water Meeting Information
Beaver Mines Water FAQ December 2022

December 8, 2022

Construction Update

December 2, 2022

The transcript from last nights meeting will be made available once all information from the Q&A session is collected. If you have further questions related to the on property work, please submit to adminutility@mdpinchercreek.ab.ca

MD Presentation
MPE Presentation
Utility Bylaw 1344-22

November 30, 2022

Construction Update - November 30, 2022

November 25, 2022

Agenda for December 1, 2022 Meeting
** Good Morning Residents,
 
Based on feedback we received, we are offering a virtual option, although in person attendance is preferred. To assist in this meeting running smoothly, and to mitigate potential technology issues, if you plan on attending virtually please pre submit any questions you may have in advance to adminutility@mdpinchercreek.ab.ca. Virtual participants will be muted.

November 14, 2022

Construction Update - November 13, 2022

November 2, 2022

Important Information - Water/Wastewater System

October 20, 2022

Notice of Construction, October 19, 2022

October 4, 2022

BYZ will be oiling the road on 2nd Ave , 4th St  and 5th St starting today (Tuesday) afternoon. It is imperative we stay off the road during this process as it can cause damage to the vehicles.

September 30, 2022

The paving company will start production on 2nd Ave starting Tuesday morning (October 4th) that will require no access on 2nd Ave until Friday. The pavement will be hot and with the magnitude of equipment in place, this is the safest approach for residents. If BYZ is able to open up sooner we will advise. Parking off of 5th St is still available.
 
If you require further information or have concerns please contact the onsite Foreman Chris: 403-502-4426 or BYZ office at 403-526-9172, Evan or Tanis will be happy to assist.

Construction Update

September 19, 2022

September 16, 2022 Construction Update

September 13, 2022

Please note that BYZ we will be starting road core and culverts today on 2nd ave which may cause delays. Each property owner will have access to their property nightly but expect delays and partial shut downs during the day to safely install culverts. Thank you for your continued patience as we continue to navigate this project.

September 2, 2022

Construction Notice

August 11, 2022

Construction Update

July 27, 2022

Servicing work on the North Section of 2nd Ave. between 4th Street & 5th Street is expected to be completed by July 29th. Upon completion, fencing will be taken down and this section of 2nd avenue will open again. Weather dependant, BYZ plans to start work on the 2nd Avenue/4th Street Section Tuesday, August 2nd

July 27, 2022 Construction Update

July 11, 2022

July 11, 2022 Construction Update

June 30, 2022

June 30 Construction Update

June 20, 2022

Recent and forecast upcoming rain has caused the schedule to slide somewhat. For the safety of the public, please be cautious of moving equipment and refrain from walking within the construction work zone.

Construction Update
Second Ave Notice

June 17, 2022

Due to weather issues, interruption in construction has taken place. BYZ will continue to monitor weather conditions over the weekend.
 
Access to the South cul-de-sac of 2nd avenue is expected to remain closed. When weather permits, the work originally scheduled to start on June 14th at the 2nd avenue and 5th street intersection will begin, which could be as early as this weekend.
 
Residents will be notified of any significant changes to this schedule and appreciate your continued patience.

June 15, 2022

Construction work originally scheduled to start on June 14th on 2nd Avenue is now expected to begin June 16th along the originally indicated corridor. Work is still expected to last 17 days, pending any more weather disruption.

2nd Ave Map

June 13, 2022

While we are so thankful for the moisture… anticipated work per last weeks update has been delayed due this weather. BYZ is monitoring weather conditions and plans to re-evaluate construction timing Wednesday. We will update once they have confirmed plans.
 
Thank you for your patience and stay safe.

June 8, 2022

June 7, 2022 Construction Update
2nd Ave Zone Notice

June 3, 2022

June 3, 2022 Construction Update

May 30, 2022

Beaver Mines May 18, 2022 Meeting Notes
May 18, 2022 Construction Map Update

May 20, 2022

Construction Update - May 20, 2022

April 13, 2022

Construction Update - April 13, 2022

December 14, 2021

Construction Update - December 10, 2021

November 15, 2021

Notice of Construction - November 15, 2021

October 26, 2021

Notice of Construction - October 26, 2021

October 13, 2021

Construction Crews will be doing work on the bulk water station on Grumpy Road (Range Road 22-A). Crews will be on site starting tomorrow (October 14, 2021) and expect to be in the area until the end of next week.

During that time the road will be open but delays could happen when trucks are coming in and out with the fill material. Disturbance should be minimal.

We appreciate your patience as we try to address these improvements. If you have any specific questions or concerns, please contact the office at 403 627-3130.

October 11, 2021

Update from BYZ

October 10, 2021

Due to scheduling, BYZ will be supplying their proposed build update schedule for the following 2 weeks by mid next week.

September 10, 2021

MD of Pincher Creek – Hamlet of Beaver Mines Potable Water Distribution & Wastewater Collection
This notice is to keep you up to date on the construction project. Currently we are completing drilling behind the tennis courts/parks area and drilling adjacent to the highway. We will begin working within the red area by our laydown on 16 September which should be completed in approximately 3 weeks. BYZ will be working on 11 & 12 September 2021. Personnel will be on site to address any questions that may arise.

September 9, 2021 Construction Notice

August 26, 2021


In an effort to keep all documents in one location, and for ease for users, the MD now has a sharepoint site we will upload relevant documents to. Below is the link to the folder with all documents from the open house in August. Please let us know if you are having trouble opening any of the documents – please note, some are large files and may take a while.
 
https://mdpinchercreekabca.sharepoint.com/:f:/s/HamletOfBeaverMinesMDOfPincherCreek/Eot83OKRJRFIhyexySA2kmABQkLpo2t6FqEnPkc2DL4fag?e=qX7IXT
 
We are striving to have progress updates and planning forecasts updated every two weeks as the project moves forward.  Please contact Mark Rowinski, of BYZ Enterprises Inc. at 403 866 2233 with any further questions regarding this project.

August 24, 2021

NOTICE OF CONSTRUCTION

MD of Pincher Creek – Hamlet of Beaver Mines Potable Water Distribution & Wastewater Collection
This notice is to inform you that we will begin construction on the above noted project. Currently our mobilization and setup dates are 19-27 August. We will begin mulching on 23-24 August 2021 in areas as aper map below. Hydrovacing and direction drilling will commence 30 August until 03 September 2021 which will limit access to the park. Personnel will be on site to address any questions that may arise.

NOTICE

July 30, 2021

Beaver Mines Water and Wastewater Community Meeting
 
Thursday August 12, 2021
4:00pm to 7:00pm
 
MD Administration Office - 1037 Herron Ave

** note: expected date to begin construction in Monday August 16, 2021
 
We want to take this opportunity to thank all of those that have worked with us to make this project a reality, especially the Beaver Mines Community Advisory Group who have reviewed and suggested changes all along the way.
 
We also would like to thank the residents for their continued patience as we go through the next couple of “build season” years as your hamlet goes through some major growing pains. 
 
If you have any questions or concerns regarding this meeting, please contact the MD office at 403 627-3130 or email info@mdpinchercreek.ab.ca

July 20, 2021

Not much new to update other than our tender for the distribution and collection has been extended to July 20th when the tenders will be opened in Lethbridge.  A short review period of the tenders will result in a successful bidder being chosen – normally a few days after the tenders are opened.  So we should have a contractor selected by the last week of July or early August.  Once this company and their availability to commence the project is determined, we will be holding an open house prior to them beginning.   Please keep an eye on this website for confirmation of the date of the open house and further updates over the summer.

July 9, 2021

Major Project Update
 
The MD of Pincher Creek No 9 has received Ministerial and Final Approval for our Beaver Mines Water and Waste Water Projects.
 
We are pleased to announce that this project will move forward and want to take this opportunity to thank all of those that have worked with us to make this project a reality, especially the Beaver Mines Community Advisory Group who have reviewed and suggested changes all along the way, that have now been incorporated into the plans with our engineers.  We also would like to thank the residents for their continued patience as we go through the next couple of “build season” years as your hamlet goes through some major growing pains.  Together, we can make this happen as painless as possible. To those that have issued Statements of Concerns, we thank you as well, for now we have an even more robust system that we can all have confidence in as we move to the next stage of the process.  This Approval clearly states that the AEP has reviewed and listened to our plans, the Statements of Concern and are confident in the system we have proposed in its planned location.  We truly look forward to bring this entire project to completion 2023.

June 28, 2021

The MD filed its updated Draft Approval and signed Letter of Understanding with the Department of Environment and Parks on Friday, June 25, 2021. The Department will now review the amended Draft with their Peer Committee and issue further changes or grant Final Approval. We are expecting to hear from the Department within the next two weeks.
 
Tenders have been released for the Distribution and Collection system work, which are not part of the Waste System that is awaiting approval. This way, work can begin in the Hamlet this summer or allow the contractors to purchase supplies and prep for Q2, 2022. Obviously, the more we get done this year, the better.
 
Grant extensions have been sought, and one has been confirmed already. We are just waiting for the other grant to be authorized to extend the project into the 2023 build year. The delays experienced to date have pushed the limits of what is realistically achievable in the time allotted, so extensions had to be sought.
 
A modified timeline will be released shortly with key benchmark dates for your information.
 
A bulk water station is currently being considered, and land is being sought with a landowner outside the Hamlet. Negotiations are ongoing, and the pre-engineered drawings/build estimates are being completed this week for presentation to Council on July 13.

May 11, 2021

Draft approval has been granted by Alberta Environment and Parks for the Beaver Mines Water and Waste Water Project.  MD Admin as well as our two engineering firms are currently reviewing the Draft Approval terms and conditions with legal counsel.  Until final approval is granted, we appreciate your continued patience as we have all taken another big step forward in making this project a reality for this Hamlet within our MD.  This draft approval truly speaks to the efforts we have all taken to ensure we are pursuing a technically and environmentally conscious system for generations to come.
 
Stay tuned…

Beaver Mines System Approval

May Update

 
We are currently awaiting AEP draft approval, which is expected imminently. Both Engineering companies are now tender ready.
 
Once draft approval is obtained, a quick window for comment or questions is held between the Department of Environment and Parks  and our engineering firms to address any questions or concerns.  Normally this takes a week or two to complete, then Final Approval can be granted. 
 
If there are no conditions on our Draft Approval we will be proceeding to tender.  If, however, there are conditions, we will wait for Final Approval before going to tender with our projects.  While the tender is out, we will complete our pre-build discussions with the BM CAG, Beaver Mines Community Advisory Group, and possibly hold another virtual open house to inform everyone of the next steps and how the project is slated to proceed.
 
With the tenders being out for 3 -4 weeks, construction is slated  in early July.  Construction will continue until September/October/ November, weather permitting.  Different parts of the project can be completed under different conditions.  We will do all we can in 2021 so that we tentatively finish all subsurface work by Aug/Sept 2022.  We are predicting that the resurfacing of the roads may carry-over to 2023.
 
We are also exploring a staged completion for anything that is done in 2021, with the possibility  that those that can be hooked up can be fully operational.  Normally a system needs to be completely installed prior to it being pressurized and operational.  We are looking at the option of seeing where we are in September to try to cap and pressurize the system at that point and make it operational for as many residents as we can for the winter of 2021/22 and then we will carry on with our work in Spring 2022 to complete the installations and hookups.   This is best case scenario only and should not be counted on by homeowners at this time, but we thought it prudent to explore the possibility.
 
Thank you for your continued patience as we strive to successfully complete the Beaver Mines Water and Wastewater projects.   We understand there is a small minority of residents opposed to these projects. We can assure you, based on science and facts we are proceeding with the most environmentally conscious and technically sound system we could find. We remain focused on delivering these services to the hamlet of Beaver Mines and look forward to the opportunity to mitigate any concerns residents/landowners may have.  We are here to serve and to work with you.  It is their right to have their voices heard and it is our responsibility to listen and address those concerns. Our focus remains on science, facts and what the majority of our residents have asked for.  I truly look forward to having a conversation with you all, so we can mend some fences; all the while delivering a state of the art system for generations to come.
 
Stay well all,
 
Troy A. MacCulloch, CMML, FSAScot
Chief Administrative Officer
Municipal District of Pincher Creek No. 9
1037 Herron Drive, PO Box 279
Pincher Creek, AB  T0K 1W0
Phone:  403.627.3130
cao@mdpinchercreek.ab.ca

Water Standpipe Survey Results - March

2021 Water Standpipe Survey Results

MD Update - February 2021 

Below is a link to a survey regarding the potential for a water standpipe near the Hamlet of Beaver Mines. Please take a moment to provide your opinion. The survey will close on March 8, 2021.
https://www.surveymonkey.com/r/StandPipe (survey closed)


Beaver Mines Distribution and Collection System:
 
Beaver Mines Liftstation, Forcemain, and Waste Water Treatment System:
 
Beaver Mines residential hookups:
Residents will be responsible for paying for that portion between the main lines and/into their homes. There will be more discussion with our residents and updates on this soon.
 
Regulatory Approvals Still Required:
Week ending November 5, 2020 - no further update on the water/wastewater project, still awaiting AEP approval

November 3, 2020,
Bylaw 1320-20 public hearing is scheduled for November 24, 2020. Please note it is in reference to the entire “Cowley - Castle Water Line”, wastewater services that already exist, and garbage collection in the collection areas throughout the MD. This bylaw is not specific to Beaver Mines.  It is our Utility bylaw for the entire MD. 
 
Due to covid restrictions, we are limiting the attendance within the MD chambers by reservation only, but will also be holding the meeting virtually.  BM residents will be involved more than most going forward as we walk through hookups, street/traffic disruptions, and everything else. These items are NOT a part of the utility bylaw.

There is no need, at this time, to flood this event with a large group from any one area.  Your participation is always welcome, but we want to ensure that everyone is aware this bylaw is for everyone and all utility services, not just BM Water and wastewater.

For more information on this public hearing please visit here.

September 4, 2020 *email to residents (to be on the email list, send a request to Communications@mdpinchercreek.ab.ca)
 
Good Afternoon Residents of Beaver Mines,
 
If you are receiving this email, is it because the MD was supplied with your email address, with your permission, via the Beaver Mines Community Association, or provided it directly to the MD for communication purposes. If you no longer wish to receive emails now or in the future, please reply and request to be removed from the information updates. We sincerely appreciate the community’s dedicated involvement, the hours that members have taken to reach out and speak with our staff, and the patience that the Beaver Mines community has had.
 
Beaver Mines Distribution and Collection System:
Beaver Mines Liftstation, Forcemain, and Waste Water Treatment System:
Regulatory Approvals Still Required: 
 Tentative Tender dates:
*All tender dates are tentative and contingent upon receipt of regulatory approvals.
 
Tentative construction dates:
 
** All construction dates are tentative and contingent upon tender, approvals, and 2021 weather.
 
If there are specific questions you have, please contact Aaron Benson at the MD at 403-627-3130 or email AdminDirOps@mdpinchercreek.ab.ca.
 
August 7, 2020 *email to residents (to be on the email list, send a request to Communications@mdpinchercreek.ab.ca)
 
Good Afternoon Residents of Beaver Mines,
 
If you are receiving this email, is it because the MD was supplied with your email address, with your permission, via the Beaver Mines Community Association, or provided it directly to the MD for communication purposes. If you no longer wish to receive emails now or in the future, please reply and request to be removed from the information updates.
 
Going forward, we want to ensure more open dialogue with the residents directly affected by this project. The updates we plan to send to the Beaver Mines list may be different from social media as they could contain more details – it is easy to miss the project update if you are not frequent on Facebook or the MD website. While no confidential information will be sent out to any resident, we feel that by having the ability to send individual emails to community members, we can ensure more coverage than can be reached with other ways of communication. We are interested to hear your thoughts and techniques that the MD can improve on communication. 
 
Castle Area Regional Water Supply Project Update (as of August 7, 2020):
Contract 2 – Mechanical:
Beaver Mines Distribution and Collection System:
 
Beaver Mines Liftstation, Forcemain, and Waste Water Treatment System:
Regulatory Approvals Still Required: 
Next Steps:
Tentative Tender dates:
*All tender dates are tentative and contingent upon receipt of regulatory approvals.
 
Tentative construction dates:
 
** All construction dates are tentative and contingent upon tender, approvals, and 2021 weather.
 
If there are specific questions you have, please contact Aaron Benson at the MD at 403-627-3130 or email AdminDirOps@mdpinchercreek.ab.ca. We sincerely appreciate the community’s involvement, the hours that dedicated members have taken to reach out and speak with our staff, and patience that the Beaver Mines community has had.
 
July 8, 2020 Website/Social Media/Pincher Creek Echo/Shootin the Breeze /posted in office

PUBLIC NOTICE
MUNICIPAL DISTRICT OF PINCHER CREEK NO. 9
ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT
NOTICE OF APPLICATION

In accordance with the Environmental Protection and Enhancement Act, the Municipal District of Pincher Creek No. 9 has applied to Alberta Environment and Parks for an approval to construct and operate the Beaver Mines Wastewater treatment plant. The wastewater treatment process includes one completely mixed aerated cell, two partially mixed aerated cells, one polishing cell, and Banner At-Grade system. The treated effluent will be disposed of to the Banner At-Grade system located at SE 16-006-02-W5M.

A directly affected person may provide input into certain regulatory decisions, as allowed by the Environmental Protection and Enhancement Act (section 73). Specifically, any person who is directly affected by this application may submit a written statement of concern within 30 days of the date of this notice to:
 
Environment and Parks
Regulatory Approvals Center
5th Floor, South Petroleum Plaza
9915 - 108 Street
Edmonton, AB T5K 2G8
Fax: (780) 422-0154
E-mail: aep.epeaapplications@gov.ab.ca
The written statement of concern should include the following:

- the application number 001-464304
- describe concerns that are relevant to matters regulated by the Environmental Protection and Enhancement Act
- explain how the filer of the concern will be directly affected by the activities proposed in the application
- provide the legal land location of the land owned or used by the filer where the concerns described are believed to be applicable
- state the distance between the land owned or used by the filer and the site in the application
- contact information including the full name and mailing address of the filer.

Please provide a telephone number and/or email address for ease of contact.

Environment and Parks will review each written statement of concern, seek more information if needed, and notify each filer by letter of the decision to accept or reject their written submission as a valid statement of concern. The Public Notice of this application will also be posted on the Department’s website at https://avw.alberta.ca/PublicNoticesViewer.aspx.

Statements of concern submitted regarding this application are public records which are accessible by the public and the applicant. Failure to file a statement of concern may affect the right to file a Notice of Appeal with the Environmental Appeals Board.

Copies of the application and additional information can be obtained from:
Municipal District of Pincher Creek No. 9
Attention: Aaron Benson

PO BOX 279
PINCHER CREEK, AB T0K 1W0
Telephone: 403-627-3130
Fax: 403-627-5070
E-mail: admindirops@mdpinchercreek.ab.ca
 
** Please note the timeline for submissions has passed and this is the process the MD is following from Alberta Environment.
 
If No Statements of Concern are received from the 30 day Public Notice
 
If Statements of Concern are received from the 30 day Public Notice
July 9, 2020 Website/Social Media
 
Please take note that starting Friday, July 10, 2020 surveyors will be in the Beaver Mines area to prepare for subsequent construction and tree removal for the installation of the water pipeline for the Castle Area Regional Water Supply along the East side of the Hamlet.
 
Construction is expected to take between three to four weeks (weather depending). As construction is within the utility right-of-way, no traffic shall be disrupted.
 
If you have any questions or concerns please contact the MD office at 403 627-3130 or email info@mdpinchercreek.ab.ca
 
July 10, 2020 Website/Social Media
 
Please take note that starting Friday, July 10, 2020 surveyors will be in the Beaver Mines area to prepare for subsequent construction and tree removal for the installation of the water pipeline for the Castle Area Regional Water Supply along the East side of the Hamlet.
 
Construction is expected to take between three to four weeks (weather depending). As construction is within the utility right-of-way, no traffic shall be disrupted.
 
If you have any questions or concerns please contact the MD office at 403 627-3130 or email info@mdpinchercreek.ab.ca
 
July 3, 2020 Website/Social Media
 
What can we say? In a word, Grateful.
 
This week it was confirmed by the Minister of Transportation, The Hon. Ric McIver, that the MD of Pincher Creek was successful in obtaining funding through the Alberta Municipal Water/Wastewater Partnership (AMWWP).  Administration applied for this grant for the Beaver Mines Wastewater Treatment Upgrade to stimulate economic recovery, support job creation, and have the funding available to complete the project without a burden to ratepayers.
 
Our Municipality will be receiving a grant of 75% the estimated eligible project costs, up to $4,561,730 for this project under AMWWP.
 
Alberta Transportation is pleased to be able to provide this funding. They recognize that supporting water and wastewater infrastructure is critical to the quality of life, economic growth, and resiliency of Alberta's communities.
 
Council acknowledges that without community support, and numerous letters to our Provincial colleagues for funding, this project wouldn't be proceeding as it is today.  We look forward to seeing this $13M project move forward.   As there are many components to the delivery of water and waste wa

Return to News & Events

Municipal District of Pincher Creek No. 9
Box 279
1037 Herron Avenue, Pincher Creek, AB T0K 1W0
Phone: 403-627-3130       Fax: 403-627-5070
Email: info@mdpinchercreek.ab.ca
Office Hours: 8:00am - 4:30pm M-F

Municipal District of Pincher Creek No. 9
Box 279
1037 Herron Avenue
Pincher Creek, AB T0K 1W0
Phone: 403-627-3130
Fax: 403-627-5070
Email: info@mdpinchercreek.ab.ca
Office Hours: 8:00am - 4:30pm M-F
Copyright © 2024 MD of Pincher Creek No. 9       Disclaimer